What each word in an operator's letter or a seller's memo means: grid-connection terms in plain words

For sellers, buyers, funds and landowners. Each term gets a short definition, the name it carries in the other three languages and a link to where you meet it on our pages.

Send us your project

Answer in brief

Each word below gets one to three plain sentences. Where an official source uses the term, its link and the day we read it follow the definition.

Your next step

A term on your papers you cannot place

Send us the project and the papers you hold. One of us reads it; nothing goes further without your agreement.

Send us your project

What happens to your enquiry →

The terms

Behind and in front of the meter

A battery behind the meter sits on the customer's side of the connection point and serves that site's own use. A battery in front of the meter connects to the public grid and sells into the market.

Also: Зад и пред електромера (BG) · Hinter und vor dem Zähler (DE) · Za i przed licznikiem (PL)

Where it comes up: seller memo

Curtailment

A cut in the power a plant or battery may feed into the grid, ordered by the grid operator or set by a market rule, so that it produces or delivers less than it could.

Also: Ограничаване на мощността (BG) · Abregelung (DE) · Redukcja produkcji (PL)

Where it comes up: Germany, large loads

Large load

A consumer that draws a large amount of power from the grid, such as a data centre. Connecting one means a request for demand, not for generation or storage.

Also: Голям потребител (BG) · Großverbraucher (DE) · Duży odbiorca (PL)

Where it comes up: Germany, large loads

Flexible connection agreement

A connection on terms that let the grid operator limit the power at times, so a site can connect even when the full capacity is not free. Source: Bundesnetzagentur, grid connection, read .

Also: Гъвкаво присъединяване (BG) · Flexible Netzanschlussvereinbarung (DE) · Elastyczna umowa przyłączeniowa (PL)

Where it comes up: Germany, large loads

Construction-cost contribution

A one-off payment to the grid operator towards the cost of the grid that serves a new connection. The German word is Baukostenzuschuss. Source: Bundesnetzagentur, construction-cost contributions, read .

Also: Участие в разходите за мрежата (BG) · Baukostenzuschuss (DE) · Dopłata do kosztów budowy sieci (PL)

Where it comes up: Germany, large loads

Substation

The grid station where lines of different voltages meet and where a battery, a solar plant or a data centre connects. If you own land near one, ask the grid operator what could connect there. Source: PSE, list of substations with no free connection places, read .

Also: Подстанция (BG) · Umspannwerk (DE) · Stacja (PL)

Where it comes up: PSE stations without free places

Connection capacity

The power, in MW, that a grid operator allows a site to feed into the grid or to draw from it. Source: ESO, connection page, read .

Also: Присъединена мощност (BG) · Netzanschlusskapazität (DE) · Moc przyłączeniowa (PL)

Where it comes up: ESO papers for a storage seller

ESO guarantee

A sum that a storage site gives ESO as security in the Bulgarian process. Check your papers for the date it was given and for who paid. Source: ESO, connection page, read .

Also: Гаранция към ЕСО (BG) · Garantie an ESO (DE) · Gwarancja dla ESO (PL)

Where it comes up: ESO papers for a storage seller

TSO and DSO

A TSO, the transmission system operator, runs the high-voltage grid; DSOs, the distribution system operators, run the regional grids below it. Source: PSE, aggregated connection information, read .

Also: Преносен и разпределителен оператор (BG) · Übertragungs- und Verteilnetzbetreiber (DE) · Spółka przesyłowa i dystrybucyjna (PL)

Where it comes up: three markets compared

Ready-to-build

A label for a project whose permits and grid connection are in hand, so that construction can start. It is a seller's word, not a document: ask for the papers behind it.

Also: Готов за строителство (BG) · Baureif (DE) · Gotowość do budowy (PL)

Where it comes up: seller memo

Connection request

The filing that starts the process: you, or your project company, ask a grid operator to connect a site at a stated capacity. A request is not an approval. Source: PSE, aggregated connection information, read .

Also: Заявка за присъединяване (BG) · Netzanschlussbegehren (DE) · Wniosek o przyłączenie (PL)

Where it comes up: ESO papers for a storage seller

Connection conditions

The grid operator's written answer to a connection request: where the project would connect, for how much capacity and on which terms. Source: PSE, aggregated connection information, read .

Also: Условия за присъединяване (BG) · Anschlussbedingungen (DE) · Warunki przyłączenia (PL)

Where it comes up: ESO papers for a storage seller

Opinion and commitment

The grid operator's written reply to a connection request. ESO in Bulgaria calls it an opinion (становище) on the conditions of connection; in Germany it is the Netzanschlusszusage, a commitment. Source: ESO, connection page, read .

Also: Становище и ангажимент (BG) · Netzanschlusszusage (DE) · Zapewnienie przyłączenia (PL)

Where it comes up: ESO papers for a storage seller

RESTORE

Bulgaria's grant programme for battery storage projects, awarded in rounds, with an approved list and a reserve list. Source: Ministry of Energy, RESTORE notice, read .

Where it comes up: RESTORE rows

Reserve list

The list of projects a round held in reserve instead of funding. If your project is on it, you have no grant yet: you can build without it, wait for freed funds or sell. Source: Ministry of Energy, RESTORE notice, read .

Also: Резервен списък (BG) · Reserveliste (DE) · Lista rezerwowa (PL)

Where it comes up: RESTORE rows

How to read the entries

The definitions are our plain-language explanations, not legal definitions and not advice. A source link points to the official page where the term appears. We give no figures, thresholds or deadlines here: those sit with their source on the pages we link.

Questions and answers

Are these legal definitions?

No. They are our plain-language explanations. For the binding meaning, read the grid operator's or the regulator's own text.

Why do some terms carry a source link and others not?

A source link points to the official page where the term appears, with the day we read it. A term without one is our plain-language explanation of a word and states nothing about a third party.

Do you give figures or deadlines for these terms?

No. Figures and deadlines stay with their source, with their date, on the pages we link.

Sources and as-of dates

  1. Bundesnetzagentur, grid connection bundesnetzagentur.de, retrieved .
  2. Bundesnetzagentur, construction-cost contributions bundesnetzagentur.de, retrieved .
  3. PSE, list of substations with no free connection places pse.pl, retrieved .
  4. ESO, connection page eso.bg, retrieved .
  5. PSE, aggregated connection information pse.pl, retrieved .
  6. Ministry of Energy, RESTORE notice me.government.bg, retrieved .