Connecting a data centre or large load in Germany? Distribution operators committed to 8% of the storage requests they received in

For landowners, developers and funds: the German connection queue that is published in numbers, what the Bundesnetzagentur says when a network operator lacks capacity, and what to put to your own in writing.

Check my plot

17,775storage requests to distribution operators in SMARD, battery-storage requests by grid level,

1,429of them received a commitmentSMARD, battery-storage requests by grid level,

383storage requests to transmission operators in SMARD, battery-storage requests by grid level,

39of them received a commitmentSMARD, battery-storage requests by grid level,

Answer in brief

If you want a large connection in Germany, you file a connection request (Netzanschlussbegehren) with your network operator. Neither the Bundesnetzagentur's connection pages (Bundesnetzagentur, Netzanschluss, read ) nor SMARD (SMARD, storage article, read ) name data centres. The one queue they put in numbers is battery storage: in distribution operators received 17,775 requests and gave 1,429 commitments, transmission operators received 383 and gave 39. If your operator cannot give you the capacity you ask for, the Bundesnetzagentur says it should examine a flexible connection agreement, but no law obliges it to offer one (Bundesnetzagentur, Netzanschluss, read ). The routes are below, with what each means for you.

Your next step

You own land near a substation

A rough location and area are enough to start. You decide afterwards whether an introduction makes sense.

Check my plot

What happens to your enquiry →

The queue you would join: storage requests by grid level

SMARD's article counts requests for commercial battery storage from medium voltage up, and its table covers only the requests that arrived in (SMARD, storage article, read ). Storage is not your load. It is the one connection queue the pages we read put in numbers, which makes it the nearest evidence of how operators answered large requests.

Battery-storage connection requests that reached network operators in , by grid level, in the figures of SMARD. The shares are SMARD's own statements.
Grid levelRequestsCapacity requestedCommitmentsCapacity committedShare of requests committedShare of requested capacityAverage size of an approved request
Distribution grid (VNB)17,775406.8 GW1,42916.8 GW8%4%14 MW
Transmission grid (ÜNB)383166.7 GW3917.2 GW10%10%384 MW

A commitment (Zusage) is a binding offer to conclude a connection contract (SMARD, storage article, read ). Developers often file several requests for one project at different sites, and where a project gets several commitments, usually one site is built (SMARD, storage article, read ). So a request count is not a project count. If a developer approaches you about your plot, ask whether it holds requests at other sites too.

For scale, SMARD quotes the Marktstammdatenregister: 1,292 battery units connected at medium voltage or above are in operation, with a net rated power of about 3.6 GW (SMARD, storage article, read ).

If your network operator cannot give you the capacity: four routes

Network operators must answer a connection request within a reasonable time (§§ 17, 18 EnWG) (Bundesnetzagentur, Netzanschluss, read ). A refusal without reasons, or on general grounds alone, does not match the aim of the law, and grid security must always be preserved (Bundesnetzagentur, Netzanschluss, read ). What you can ask for instead:

Routes when the capacity you ask for is not available, as the Bundesnetzagentur describes them.
RouteWhat the Bundesnetzagentur statesWhat it means for you
Flexible connection agreement (FCA)It serves to allow connections with restrictions where capacity is scarce, and § 17 para. 2b EnWG regulates it (Bundesnetzagentur, Netzanschluss, read ). The restriction can be constant or apply at times, and it can be limited in time, for example until the grid is expanded, or permanent (Bundesnetzagentur, Netzanschluss, read ).Ask for the limit in writing: how large, at which hours, for how long.
Several installations on one connection (co-location)An FCA can also connect several installations, for example with a storage unit, at one shared connection (Bundesnetzagentur, Netzanschluss, read ).If your plot could carry more than one installation, say so in your request.
Abuse complaint (Missbrauchsantrag)It is a formal legal procedure that takes much time, does not speed up your request and does not change the scarcity of capacity (Bundesnetzagentur, Netzanschluss, read ). Even a successful one would bring no better legal position than other applicants have (Bundesnetzagentur, Netzanschluss, read ).Do not rely on it to move you up the queue.
Model contracts through the associationsDeveloping model FCA contracts through the operators' and connected parties' associations is more promising than abuse complaints, and the Bundesnetzagentur supports it (Bundesnetzagentur, Netzanschluss, read ).Ask your operator whether it works with a model FCA contract.

The Bundesnetzagentur adds that there is currently the option, but no explicit legal duty, for operators to offer an FCA (Bundesnetzagentur, Netzanschluss, read ), and that the details are agreed by contract between you and your network operator (Bundesnetzagentur, Netzanschluss, read ). It separates an FCA, a contractual restriction of the connection in advance, from redispatch, a measure within network use (Bundesnetzagentur, Netzanschluss, read ).

What it costs: the construction cost contribution

The Bundesnetzagentur describes the Baukostenzuschuss as a one-off payment for expanding the general grid, paid to the network operator when the connection is made (Bundesnetzagentur, Baukostenzuschüsse, read ). In low voltage it may be levied only on the part of the capacity requirement above 30 kW (Bundesnetzagentur, Baukostenzuschüsse, read ). The pages we read name no amount and no threshold for medium or high voltage, so we show none. In a dispute over the reasonable amount, the case-law principles on a one-sided right to set the performance (§ 315 BGB) apply (Bundesnetzagentur, Baukostenzuschüsse, read ).

Ask your network operator in writing

  • Which connection point do you have in mind, and is the capacity you need available there? From when?
  • If not in full: would you offer a flexible connection agreement? With which limit, at which hours, until when?
  • How do you calculate the construction cost contribution for this capacity, and when is it due?
  • If a developer asks for your plot: does it hold requests at other sites for the same project?
  • Date every reply and keep it with your request.

Check my plot

What nobody publishes

On we read the Bundesnetzagentur's connection page, its page on construction cost contributions and the SMARD article. None of them names data centres, and none gives a number of large loads waiting for a connection. We do not estimate one. We read the three pages again every day.

Questions and answers

Does Germany publish how many data centres wait for a grid connection?

Not on the pages we read: the Bundesnetzagentur's connection pages (Bundesnetzagentur, Netzanschluss, read ) and SMARD (SMARD, storage article, read ) name no data centres.

Do the storage figures describe my load?

No. They count requests for battery storage from medium voltage up, split by grid level (SMARD, storage article, read ). We show them because they are the connection queue the pages we read put in numbers.

Can I get a connection with restrictions?

The Bundesnetzagentur describes flexible connection agreements for storage and consumption facilities, and says operators have the option but no explicit legal duty to offer one (Bundesnetzagentur, Netzanschluss, read ).

Do I pay for the connection?

The Bundesnetzagentur describes a one-off construction cost contribution for expanding the general grid (Bundesnetzagentur, Baukostenzuschüsse, read ). Ask your operator how it calculates the amount for your capacity.

Sources and as-of dates

  1. SMARD, battery-storage requests by grid level: smard.de, retrieved .
  2. Bundesnetzagentur, construction cost contributions (Baukostenzuschüsse): bundesnetzagentur.de, retrieved .
  3. Bundesnetzagentur, Netzanschluss bundesnetzagentur.de, retrieved .
  4. Bundesnetzagentur, Baukostenzuschüsse bundesnetzagentur.de, retrieved .
  5. SMARD, battery storage connection requests smard.de, retrieved .