ESO's page names a guarantee of 50,000 leva per MW for a storage site: what that comes to on your project, before you sell it

A calculator for your MW, the papers that show the guarantee was given, and the portal rules.

Show us your project

50,000 leva per MWguarantee ESO's page names for whoever runs a storage site, per MW of connected capacityESO, connection page,

Answer in brief

ESO's connection page names a guarantee for a storage site: 50,000 leva per MW (ESO, connection page, ) Earlier value: 50,000 leva per MW () (ESO, ). Type your MW into the calculator to see the sum, then check the grid file below paper by paper.

Your next step

Your guarantee is with ESO

Send us your MW and the date you gave the guarantee. One of us reads it; nothing is passed on unless you agree.

Show us your project

What happens to your enquiry →

The guarantee on your MW

Enter your capacity. We ask who gave this guarantee and when, so work out the sum before you write to us.

Guarantee to ESO:

How it is worked out: the MW you enter times the amount per MW from ESO's page (ESO, ). The arithmetic is ours; the amount is in leva as ESO gives it, and we do not convert it to euro.

The guarantee at common sizes. Method: capacity in MW times the amount per MW from ESO's page (ESO, ); the arithmetic is ours
CapacityGuarantee to ESO
1 MW50,000 leva
5 MW250,000 leva
10 MW500,000 leva
20 MW1,000,000 leva
50 MW2,500,000 leva
100 MW5,000,000 leva

The grid file: four papers to hold before you call

We ask for these when you send us a project. A gap is fine; tell us which papers you hold and which you do not.

The seller's grid file: what to hold, and what ESO's page states. The check column is our own advice
PaperWhat to check (our advice)What ESO's page states
ESO's opinion on the conditions and manner of connectionIts date, the substation and the MW it states, copied exactly as written, and the company it is issued to.The guarantee for a storage site is given within three months of receiving the opinion (ESO, ).
Proof the guarantee was givenIts date and who paid. If the company will change hands, ask ESO or your lawyer in writing what happens to the guarantee.Whoever runs a storage site gives ESO a guarantee of 50,000 leva per MW (ESO, connection page, ) Earlier value: 50,000 leva per MW () (ESO, ).
Your registration in ESO's portalWho is registered: your project company, or an adviser with a notarised power of attorney. If an adviser, agree in writing that the file passes to the buyer.ESO's page describes access to the portal like this: registration by the applicant, or by an authorised person with a notarised power of attorney, with a qualified electronic signature (ESO, ).
The project memoThe one page with your MW, your stage and your papers that you hand to a buyer.Our own list: we cite no official page for this step.

If your project sits on a RESTORE reserve list

The counts below come from the RESTORE lists we already track. Read them before you decide to build without the grant, wait, or sell.

RESTORE reserve-list rows, and whether the company that holds them also has a funded project. Sources: ISUN, RESTORE round-one ranking, ; Ministry of Energy, RESTORE second-round lists, . Companies are matched by company number
Reserve listRowsCompany with no funded projectCompany with a funded project
Round one30300
Round two30255

Batteries already running: NetZeroLab, Sofia University writes on that operating battery power in Bulgaria is about 5.4 GW, against about 1.4 GW in , citing ENTSO-E. We have not checked this against ENTSO-E (read ).

Questions to put to ESO in writing

These are our questions, not statements about ESO. Ask them by letter or through the portal, and keep the replies in the file.

  • Does the opinion name the company you are selling, and the same MW as your project?
  • Is the guarantee for your MW received and recorded, and in whose name?
  • What happens to the guarantee and to the registration if the company changes owner?

The words on the papers

The Bulgarian words on ESO's papers, in plain English (our own glosses)
Word on the paperWhat it meansWhere to look for it
заявител (applicant)The company or person that filed the connection request.In the heading of the opinion and in the portal registration.
становище (opinion)ESO's written reply to the request.In the project company's mail; ask the adviser too.
гаранция (guarantee)The sum a storage site gives ESO.On the receipt or the bank notice.
пълномощно (power of attorney)A written authority for another person to act for you.In the adviser's file, if the adviser registered for you.
КЕП (qualified electronic signature)The signature type a form for the portal is signed with.With the authorised person, or with your company's manager.
присъединена мощност (connected capacity)The MW the storage site is connected for, the figure the guarantee is counted on.In the opinion, next to the substation's name.
обект за съхранение (storage site)A site that stores electricity, as a battery does.In the heading of the opinion and in the guarantee receipt.
подстанция (substation)The grid station where your site would connect.In the opinion, next to the MW.
ЕСО ЕАДThe company form of ESO, written after its name.After ESO's name on the papers you hold.
Информационен портал (information portal)The ESO website where an applicant registered with a signature gets access.At the address of ESO's connection page, linked in the table above.

Before the portal: the browser

Whoever registers you will need a browser ESO accepts.

What ESO's portal needs, as ESO's page states it, with the day we read it
RequirementWhat ESO's page states
BrowserChrome 70+, Edge 79+, Safari 14.1+ or Opera 57+; Internet Explorer is not supported (ESO, ).

Papers in hand? Show us your project. The page you hand to a buyer is our seller memo. We do not value projects, give legal or tax advice, or publish asking prices.

Questions and answers

Does the ESO guarantee apply to a solar plant?

ESO's page states it for a storage site (ESO, ). For a solar plant, ask ESO.

Does the guarantee pass to a buyer with the company?

We cannot tell you. Ask ESO or your lawyer in writing before you sign with a buyer, and put the answer in your file.

Sources and as-of dates

  1. ESO, connection page: eso.bg, retrieved .
  2. ESO, connection page: eso.bg, retrieved .
  3. ESO, connection page: eso.bg, retrieved .
  4. Balkan Green Energy News, RESTORE round results: balkangreenenergynews.com, retrieved .
  5. ISUN, RESTORE round-one ranking: 2020.eufunds.bg, retrieved .
  6. Ministry of Energy, notice on the second RESTORE procedure: me.government.bg, retrieved .
  7. Ministry of Energy, RESTORE second-round lists: me.government.bg, retrieved .
  8. NetZeroLab, Sofia University, citing ENTSO-E: netzerolab-feba.bg, retrieved .