Answer in brief
If your data centre or other large consumer connects to a grid above 1 kV, PSE states that you pay 1 zł per kW of requested capacity just to apply, up to 100 000 zł, and an advance of 60 zł per kW, up to 6 000 000 zł per connection (PSE communiqué, ). Connection conditions issued now stay valid 1 year, not 2. Neither PSE nor the regulator URE states a data-centre figure on the pages we read. The table below works out what you pay at fourteen load sizes, with the method beside each amount.
Your next step
Selling, buying, investing or holding land?
Three short forms, and we read every enquiry ourselves.
What happens to your enquiry →What changed for applicants on
PSE summarised the changes to the connection process for applicants in a communiqué. For anyone applying to a grid above 1 kV (PSE communiqué, ), consumers included, it states these changes:
| Rule | Before | Since |
|---|---|---|
| Application fee | New in the communiqué | 1 zł per kW requested, at most 100 000 zł |
| Advance on the connection charge | 30 zł per kW | 60 zł per kW, at most 6 000 000 zł per connection |
| Validity of connection conditions | 2 years | 1 year |
PSE adds that the advance now covers everyone applying above that voltage, and names electricity consumers in particular.
What you pay at fourteen load sizes
We applied PSE's rates to fourteen sizes we picked. The last column adds the fee and the advance. The fee is the smaller of 1 zł (PSE communiqué, ) times the kilowatts you request and 100 000 zł. The advance is the smaller of 60 zł times the kilowatts and 6 000 000 zł. Both ceilings are reached at 100 MW: 100 000 zł divided by 1 zł per kW is the same load as 6 000 000 zł divided by 60 zł per kW. Above that size the amounts stop rising.
| Load size (our example) | Application fee | Advance | Total due with the application |
|---|---|---|---|
| 1 MW | 1 000 zł | 60 000 zł | 61 000 zł |
| 2 MW | 2 000 zł | 120 000 zł | 122 000 zł |
| 5 MW | 5 000 zł | 300 000 zł | 305 000 zł |
| 10 MW | 10 000 zł | 600 000 zł | 610 000 zł |
| 15 MW | 15 000 zł | 900 000 zł | 915 000 zł |
| 20 MW | 20 000 zł | 1 200 000 zł | 1 220 000 zł |
| 30 MW | 30 000 zł | 1 800 000 zł | 1 830 000 zł |
| 40 MW | 40 000 zł | 2 400 000 zł | 2 440 000 zł |
| 50 MW | 50 000 zł | 3 000 000 zł | 3 050 000 zł |
| 60 MW | 60 000 zł | 3 600 000 zł | 3 660 000 zł |
| 75 MW | 75 000 zł | 4 500 000 zł | 4 575 000 zł |
| 100 MW | 100 000 zł | 6 000 000 zł | 6 100 000 zł |
| 150 MW | 100 000 zł | 6 000 000 zł | 6 100 000 zł |
| 200 MW | 100 000 zł | 6 000 000 zł | 6 100 000 zł |
For a load above 100 MW the amounts are the same as at that size, because both ceilings apply.
What PSE's impact expertise has to cover
For a connection to PSE's grid at 110 kV (PSE communiqué on impact expertises, ) or higher, PSE's scope document sets what the impact expertise must contain. The overload tolerance is the figure to watch. If a transmission-grid element was not overloaded before your connection and carries more than its permitted current by over 2 A (PSE, impact expertise scope, ) afterwards (2 MVA for transformers), the document counts that as a threat your connection introduces. So does an existing overload that deepens by more than the same tolerance.
| Part | What it covers |
|---|---|
| I | The technical specification of your installation, taken from your application. |
| II | Guidelines for the calculations: how your installation and its neighbours are loaded in each scenario, and which parts of the grid are observed. |
| III | Load-flow analysis in the high-voltage and extra-high-voltage grid, in normal and emergency states. |
| IV | The voltage levels at grid nodes that result from your connection. |
| V | Short-circuit calculations and the assessment of your installation's impact on the grid. |
| VI | The conclusions, including the investments your connection requires. |
PSE's terms, in plain English
- Opłata za wniosek
- The application fee: paid when you file, per kW, with a ceiling.
- Zaliczka
- The advance on your connection charge: paid on top of the fee, per kW, per connection, with a ceiling.
- Warunki przyłączenia
- The connection conditions PSE issues when it accepts your application. They are valid for a limited period, shown in the table above.
- ESOP
- PSE's online portal for connection applications.
If you filed before
PSE gives applicants whose request was not yet decided 60 (PSE communiqué, ) days to pay the application fee. Conditions issued before keep the validity written in them: 2 years (PSE communiqué, ) from delivery.
Where you file
PSE's announcement of its online portal ESOP says new applications for connection conditions go through that portal only, from .
What PSE and URE do not publish about data centres
On we read PSE's connection pages, its page on available connection capacity and URE's news page. None states a figure for data centres or for the number of large loads waiting for a connection. The capacity document lists what PSE can offer to generating sources, so it does not answer a consumer's question. That is why you find no data-centre table here. We read PSE's pages every day and add a figure, with its source and date, the day one appears. If your question is about one station, PSE's own list of full switchgear is the page to open. Comparing with another market? Bulgaria's data-centre connection requests sit on their own page.
Questions and answers
Do the fee and the advance apply to my data centre?
PSE states them for anyone applying to a grid above 1 kV, consumers included. Whether your connection is above that depends on the voltage at your connection point, so ask the grid company.
Are these the final amounts?
They are the rates and ceilings in PSE's communiqué of , which tells applicants to read the full act themselves. Check the act and PSE's current page before you pay.
Does PSE publish how many data centres are waiting?
Not on the pages we read. We say so rather than estimate.
Does my distribution operator charge the same?
The communiqué is PSE's, for its transmission grid. We hold no source for a distribution operator's amounts, so we show none.
Sources and as-of dates
- PSE communiqué: pse.pl, retrieved .
- our calculation from the PSE communiqué: pse.pl, retrieved .
- PSE communiqué on impact expertises: pse.pl, retrieved .
- PSE, impact expertise scope: pse.pl, retrieved .
- PSE, announcement of the online connection portal ESOP pse.pl, retrieved .
- PSE, page on available connection capacity pse.pl, retrieved .
- URE, news page ure.gov.pl, retrieved .