Connecting a large load in Poland: PSE asks 1 zł per kW to apply and 60 zł per kW as an advance

For developers, funds and landowners planning a data centre or another large consumer: what PSE states you pay, how long your conditions last, and which figures nobody publishes.

Choose your form

60 złper kW: the advance PSE asks with an application, per connectionPSE communiqué,

100 000 złthe ceiling on the application feePSE communiqué,

100 MWthe load size at which both ceilings are reached (our calculation)our calculation from the PSE communiqué,

1year of validity for connection conditions issued from PSE communiqué,

Answer in brief

If your data centre or other large consumer connects to a grid above 1 kV, PSE states that you pay 1 zł per kW of requested capacity just to apply, up to 100 000 zł, and an advance of 60 zł per kW, up to 6 000 000 zł per connection (PSE communiqué, ). Connection conditions issued now stay valid 1 year, not 2. Neither PSE nor the regulator URE states a data-centre figure on the pages we read. The table below works out what you pay at fourteen load sizes, with the method beside each amount.

Your next step

Selling, buying, investing or holding land?

Three short forms, and we read every enquiry ourselves.

Choose your form

What happens to your enquiry →

What changed for applicants on

PSE summarised the changes to the connection process for applicants in a communiqué. For anyone applying to a grid above 1 kV (PSE communiqué, ), consumers included, it states these changes:

Connection rules for applicants above 1 kV, as PSE's communiqué of states them.
RuleBeforeSince
Application feeNew in the communiqué1 zł per kW requested, at most 100 000 zł
Advance on the connection charge30 zł per kW60 zł per kW, at most 6 000 000 zł per connection
Validity of connection conditions2 years1 year

PSE adds that the advance now covers everyone applying above that voltage, and names electricity consumers in particular.

What you pay at fourteen load sizes

We applied PSE's rates to fourteen sizes we picked. The last column adds the fee and the advance. The fee is the smaller of 1 zł (PSE communiqué, ) times the kilowatts you request and 100 000 zł. The advance is the smaller of 60 zł times the kilowatts and 6 000 000 zł. Both ceilings are reached at 100 MW: 100 000 zł divided by 1 zł per kW is the same load as 6 000 000 zł divided by 60 zł per kW. Above that size the amounts stop rising.

What PSE's rates give for one connection point and one connection. The sizes are our examples; the amounts are our calculation from the communiqué of . The sign zł is the Polish złoty.
Load size (our example)Application feeAdvanceTotal due with the application
1 MW1 000 zł60 000 zł61 000 zł
2 MW2 000 zł120 000 zł122 000 zł
5 MW5 000 zł300 000 zł305 000 zł
10 MW10 000 zł600 000 zł610 000 zł
15 MW15 000 zł900 000 zł915 000 zł
20 MW20 000 zł1 200 000 zł1 220 000 zł
30 MW30 000 zł1 800 000 zł1 830 000 zł
40 MW40 000 zł2 400 000 zł2 440 000 zł
50 MW50 000 zł3 000 000 zł3 050 000 zł
60 MW60 000 zł3 600 000 zł3 660 000 zł
75 MW75 000 zł4 500 000 zł4 575 000 zł
100 MW100 000 zł6 000 000 zł6 100 000 zł
150 MW100 000 zł6 000 000 zł6 100 000 zł
200 MW100 000 zł6 000 000 zł6 100 000 zł

For a load above 100 MW the amounts are the same as at that size, because both ceilings apply.

What PSE's impact expertise has to cover

For a connection to PSE's grid at 110 kV (PSE communiqué on impact expertises, ) or higher, PSE's scope document sets what the impact expertise must contain. The overload tolerance is the figure to watch. If a transmission-grid element was not overloaded before your connection and carries more than its permitted current by over 2 A (PSE, impact expertise scope, ) afterwards (2 MVA for transformers), the document counts that as a threat your connection introduces. So does an existing overload that deepens by more than the same tolerance.

The six parts of PSE's scope document for the impact expertise.
PartWhat it covers
IThe technical specification of your installation, taken from your application.
IIGuidelines for the calculations: how your installation and its neighbours are loaded in each scenario, and which parts of the grid are observed.
IIILoad-flow analysis in the high-voltage and extra-high-voltage grid, in normal and emergency states.
IVThe voltage levels at grid nodes that result from your connection.
VShort-circuit calculations and the assessment of your installation's impact on the grid.
VIThe conclusions, including the investments your connection requires.

PSE's terms, in plain English

Opłata za wniosek
The application fee: paid when you file, per kW, with a ceiling.
Zaliczka
The advance on your connection charge: paid on top of the fee, per kW, per connection, with a ceiling.
Warunki przyłączenia
The connection conditions PSE issues when it accepts your application. They are valid for a limited period, shown in the table above.
ESOP
PSE's online portal for connection applications.

If you filed before

PSE gives applicants whose request was not yet decided 60 (PSE communiqué, ) days to pay the application fee. Conditions issued before keep the validity written in them: 2 years (PSE communiqué, ) from delivery.

Where you file

PSE's announcement of its online portal ESOP says new applications for connection conditions go through that portal only, from .

What PSE and URE do not publish about data centres

On we read PSE's connection pages, its page on available connection capacity and URE's news page. None states a figure for data centres or for the number of large loads waiting for a connection. The capacity document lists what PSE can offer to generating sources, so it does not answer a consumer's question. That is why you find no data-centre table here. We read PSE's pages every day and add a figure, with its source and date, the day one appears. If your question is about one station, PSE's own list of full switchgear is the page to open. Comparing with another market? Bulgaria's data-centre connection requests sit on their own page.

Questions and answers

Do the fee and the advance apply to my data centre?

PSE states them for anyone applying to a grid above 1 kV, consumers included. Whether your connection is above that depends on the voltage at your connection point, so ask the grid company.

Are these the final amounts?

They are the rates and ceilings in PSE's communiqué of , which tells applicants to read the full act themselves. Check the act and PSE's current page before you pay.

Does PSE publish how many data centres are waiting?

Not on the pages we read. We say so rather than estimate.

Does my distribution operator charge the same?

The communiqué is PSE's, for its transmission grid. We hold no source for a distribution operator's amounts, so we show none.

Sources and as-of dates

  1. PSE communiqué: pse.pl, retrieved .
  2. our calculation from the PSE communiqué: pse.pl, retrieved .
  3. PSE communiqué on impact expertises: pse.pl, retrieved .
  4. PSE, impact expertise scope: pse.pl, retrieved .
  5. PSE, announcement of the online connection portal ESOP pse.pl, retrieved .
  6. PSE, page on available connection capacity pse.pl, retrieved .
  7. URE, news page ure.gov.pl, retrieved .