Answer in brief
If a developer has approached you about your land, ask first which of two groups the project is in. CMS Bulgaria reports, citing ESO data, that applications and investment intentions to connect data centres to the transmission grid totalled 9,330 MW (CMS Bulgaria, legal update on data centres, ) as at . ESO has issued opinions on the connection conditions for 3,795 MW (CMS Bulgaria, legal update on data centres, ) of that total, and 5,535 MW (CMS Bulgaria, legal update on data centres, ) are at the stage of investment intentions.
So an offer for your plot can sit on either side of that line. Ask the developer to show you the ESO opinion, and ask ESO in writing what it can say about your plot.
Your next step
You own land near a substation
A rough location and area are enough to start. You decide afterwards whether an introduction makes sense.
What happens to your enquiry →The request list, stage by stage
| Stage | Volume | As at | Source |
|---|---|---|---|
| Applications and investment intentions to connect data centres to the transmission grid | 9,330 MW | CMS Bulgaria | |
| Of that total, with an ESO opinion on the connection conditions | 3,795 MW | Update of | CMS Bulgaria |
| Of that total, at the stage of investment intentions | 5,535 MW | Update of | CMS Bulgaria |
| The country's peak winter consumption, which CMS gives for comparison | about 7,000 MW | Update of | CMS Bulgaria |
We opened the CMS page on and took each figure from it. CMS cites ESO data for the total.
Where the requests sit, region by region
CMS reports that demand is concentrated in Plovdiv, Burgas and Pleven, with the volumes below. Check whether your plot lies in or near one of them.
| Region | Demand | Source |
|---|---|---|
| Plovdiv | 2.26 GW | CMS Bulgaria |
| Burgas | 1.86 GW | CMS Bulgaria |
| Pleven | 1.14 GW | CMS Bulgaria |
What ESO issues to data centres
According to CMS, large consumers apply to ESO under the connection ordinance (Ordinance No. 6), and ESO does not conclude preliminary connection contracts with data-centre applicants. It issues opinions on the conditions for connection instead, and those are valid for 1 year (CMS Bulgaria, legal update on data centres, ).
CMS also notes that whether a project progresses within that period depends on the investor, and that the volume of requests exceeds the capacity of the system by a wide margin. It adds that market participants have raised concerns that part of the requested capacity is speculative.
What this means if you hold land near a substation
- An opinion on connection conditions is not a connection contract. If a developer says it has "grid", ask to see the ESO opinion itself.
- Read the date on the opinion. Per CMS it is valid for 1 year (CMS Bulgaria, legal update on data centres, ), so the date tells you how much of that period is left.
- Ask which stage the project is in. ESO has issued opinions for 3,795 MW (CMS Bulgaria, legal update on data centres, ) of the total, and the rest is at the stage of investment intentions.
- Write to ESO about your plot and your nearest substation, and keep the reply with its date. We quote no free-capacity figure for any substation, because we hold no source for one.
- Before you sign an exclusivity or an option, read it with a lawyer. Tell the developer only what you hold in writing, and say what you do not know.
We publish no sale price or rent for land near a substation, because we hold no source for one.
Tell us about your plot
To start, we need your name, your email, and for the plot its country, location, area, owner type and what interests you. We read every enquiry ourselves, and we share nothing without your agreement.
Questions and answers
Whose figures are these?
They come from a CMS Bulgaria legal update of , which cites ESO data for the total. We link the page so that you can read each sentence yourself.
Do these totals tell me anything about my plot?
No. They show how long the request list is. Only ESO's written answer on your plot tells you about your plot.
Does an ESO opinion mean the data centre will be built?
No. CMS says whether a project progresses within the period of the opinion depends on the investor. Ask the developer what happens next, and in writing.
Do you buy or sell land?
No. We read your enquiry ourselves and decide case by case whether an introduction makes sense. A fee, if one ever applies, is agreed with you in writing before any name is shared.
Sources and as-of dates
- CMS Bulgaria, legal update on data centres: cms.law, retrieved .